Task Title:GDW MFG UI Style Guide + Prep |
Status: Done |
Start Date:10/17/2023 |
Due Date:10/19/2023 |
Duration:2 Days |
Date Completed:10/04/2023 |
Task Title:GDW MFG Homepage + Foundation Buildout |
Status: Done |
Start Date:10/20/2023 |
Due Date:10/26/2023 |
Duration:6 Days |
Date Completed:10/04/2023 |
Task Title:GDW MFG Homepage Design Client Review ☎️ |
Status: Done |
Start Date:10/27/2023 |
Due Date:10/31/2023 |
Duration:4 Days |
Date Completed:10/04/2023 |
Task Title:GDW MFG Sub Pages Buildout |
Status: Done |
Start Date:11/01/2023 |
Due Date:11/16/2023 |
Duration:15 Days |
Date Completed:11/15/2023 |
Task Title:GDW MFG Content Implementation |
Status: Done |
Start Date:11/17/2023 |
Due Date:11/22/2023 |
Duration:5 Days |
Date Completed:11/22/2023 |
Task Title:GDW MFG Internal QA |
Status: Done |
Start Date:11/27/2023 |
Due Date:11/29/2023 |
Duration:2 Days |
Date Completed:11/22/2023 |
Task Title:GDW MFG Presentation + Client Review ☎️ |
Status: Done |
Start Date:11/30/2023 |
Due Date:12/19/2023 |
Duration:19 Days |
Date Completed:12/05/2023 |
Task Title:Staging edits |
Status: Done |
Start Date:03/15/2024 |
Due Date:03/19/2024 |
Duration:4 Days |
Date Completed:03/27/2024 |
Task Title:GDW MFG Client Training & Access |
Status: Awaiting Client |
Start Date:03/27/2024 |
Due Date:03/28/2024 |
Duration:1 Days |
Date Completed: |
Task Title:GDW MFG Launch 🚀 |
Status: Done |
Start Date:03/27/2024 |
Due Date:03/27/2024 |
Duration:1 Days |
Date Completed:03/28/2024 |
Task Title:GDW MFG Post-Launch Followup copy |
Status: Awaiting Client |
Start Date:04/01/2024 |
Due Date:04/02/2024 |
Duration:1 Days |
Date Completed: |