Task Title:Research |
Status: Done |
Start Date:03/07/2022 |
Due Date:03/18/2022 |
Duration:11 Days |
Date Completed:03/22/2022 |
Task Title:Client Questionnaire |
Status: Done |
Start Date:03/07/2022 |
Due Date:03/09/2022 |
Duration:2 Days |
Date Completed:03/08/2022 |
Task Title:Client Kickoff Meeting |
Status: Done |
Start Date:03/15/2022 |
Due Date:03/15/2022 |
Duration:1 Days |
Date Completed:03/14/2022 |
Task Title:Keyword Research |
Status: Done |
Start Date:03/16/2022 |
Due Date:03/18/2022 |
Duration:2 Days |
Date Completed:03/21/2022 |
Task Title:Collect Technical Files & Assets |
Status: Done |
Start Date:03/16/2022 |
Due Date:03/18/2022 |
Duration:2 Days |
Date Completed:03/21/2022 |
Task Title:Planning |
Status: Done |
Start Date:03/21/2022 |
Due Date:03/29/2022 |
Duration:8 Days |
Date Completed:04/11/2022 |
Task Title:Sitemap |
Status: Done |
Start Date:03/21/2022 |
Due Date:03/28/2022 |
Duration:7 Days |
Date Completed:04/05/2022 |
Task Title:Outline + URLs for Sitemap |
Status: Done |
Start Date:03/21/2022 |
Due Date:03/22/2022 |
Duration:1 Days |
Date Completed:03/22/2022 |
Task Title:Sitemap |
Status: Done |
Start Date:03/23/2022 |
Due Date:03/24/2022 |
Duration:1 Days |
Date Completed:03/24/2022 |
Task Title:Client Review/Approval |
Status: Done |
Start Date:04/07/2022 |
Due Date:04/08/2022 |
Duration:1 Days |
Date Completed:04/05/2022 |
Task Title:Final Content Collection ✍️ |
Status: Done |
Start Date:04/05/2022 |
Due Date:04/05/2022 |
Duration:1 Days |
Date Completed:04/08/2022 |
Task Title:Web Design |
Status: Done |
Start Date:03/30/2022 |
Due Date:05/09/2022 |
Duration:40 Days |
Date Completed:05/19/2022 |
Task Title:Home Page |
Status: Done |
Start Date:03/30/2022 |
Due Date:04/07/2022 |
Duration:8 Days |
Date Completed:04/18/2022 |
Task Title:Homepage Design |
Status: Done |
Start Date:04/08/2022 |
Due Date:04/12/2022 |
Duration:4 Days |
Date Completed:04/11/2022 |
Task Title:Internal Review / QA |
Status: Done |
Start Date:04/13/2022 |
Due Date:04/13/2022 |
Duration:1 Days |
Date Completed:04/15/2022 |
Task Title:Homepage / Direction Review with Client |
Status: Done |
Start Date:04/14/2022 |
Due Date:04/14/2022 |
Duration:1 Days |
Date Completed:04/14/2022 |
Task Title:Client Review / Approval |
Status: Done |
Start Date:04/19/2022 |
Due Date:04/20/2022 |
Duration:1 Days |
Date Completed:04/18/2022 |
Task Title:Blog Landing Page |
Status: Done |
Start Date:04/19/2022 |
Due Date:05/12/2022 |
Duration:23 Days |
Date Completed:05/19/2022 |
Task Title:Design |
Status: Done |
Start Date:04/19/2022 |
Due Date:04/26/2022 |
Duration:7 Days |
Date Completed:05/01/2022 |
Task Title:Internal Review / QA |
Status: Done |
Start Date:04/27/2022 |
Due Date:04/28/2022 |
Duration:1 Days |
Date Completed:05/01/2022 |
Task Title:Client Review / Approval |
Status: Done |
Start Date:05/06/2022 |
Due Date:05/09/2022 |
Duration:3 Days |
Date Completed:05/12/2022 |
Task Title:Blog Detail Page |
Status: Done |
Start Date:04/19/2022 |
Due Date:05/12/2022 |
Duration:23 Days |
Date Completed:05/19/2022 |
Task Title:Design |
Status: Done |
Start Date:04/19/2022 |
Due Date:04/26/2022 |
Duration:7 Days |
Date Completed:05/01/2022 |
Task Title:Internal Review / QA |
Status: Done |
Start Date:04/27/2022 |
Due Date:04/28/2022 |
Duration:1 Days |
Date Completed:05/01/2022 |
Task Title:Client Review / Approval |
Status: Done |
Start Date:04/29/2022 |
Due Date:05/11/2022 |
Duration:12 Days |
Date Completed:05/12/2022 |
Task Title:Initiatives Detail Page |
Status: Done |
Start Date:04/19/2022 |
Due Date:05/12/2022 |
Duration:23 Days |
Date Completed:05/19/2022 |
Task Title:Design |
Status: Done |
Start Date:04/29/2022 |
Due Date:05/10/2022 |
Duration:11 Days |
Date Completed:05/19/2022 |
Task Title:Internal Review / QA |
Status: Done |
Start Date:05/11/2022 |
Due Date:05/12/2022 |
Duration:1 Days |
Date Completed:05/19/2022 |
Task Title:Client Review / Approval |
Status: Done |
Start Date:05/13/2022 |
Due Date:05/18/2022 |
Duration:5 Days |
Date Completed:05/19/2022 |
Task Title:Estuary Science or Impact Page |
Status: Done |
Start Date:04/21/2022 |
Due Date:05/12/2022 |
Duration:21 Days |
Date Completed:05/19/2022 |
Task Title:Design |
Status: Done |
Start Date:04/19/2022 |
Due Date:04/26/2022 |
Duration:7 Days |
Date Completed:05/01/2022 |
Task Title:Internal Review / QA |
Status: Done |
Start Date:04/27/2022 |
Due Date:04/28/2022 |
Duration:1 Days |
Date Completed:05/01/2022 |
Task Title:Client Review / Approval |
Status: Done |
Start Date:04/29/2022 |
Due Date:05/12/2022 |
Duration:13 Days |
Date Completed:05/16/2022 |
Task Title:Web Dev |
Status: In Progress |
Start Date:05/10/2022 |
Due Date:06/09/2022 |
Duration:30 Days |
Date Completed: |
Task Title:Asset Optimization |
Status: Done |
Start Date:04/29/2022 |
Due Date:04/29/2022 |
Duration:1 Days |
Date Completed:05/25/2022 |
Task Title:Foundational Development / Coding |
Status: Done |
Start Date:05/10/2022 |
Due Date:05/17/2022 |
Duration:7 Days |
Date Completed:05/25/2022 |
Task Title:Page Templates + Generic Styles |
Status: Done |
Start Date:05/18/2022 |
Due Date:05/25/2022 |
Duration:7 Days |
Date Completed:05/25/2022 |
Task Title:Content Implementation |
Status: Done |
Start Date:05/26/2022 |
Due Date:05/30/2022 |
Duration:4 Days |
Date Completed:06/21/2022 |
Task Title:Developer QA |
Status: In Progress |
Start Date:05/31/2022 |
Due Date:06/01/2022 |
Duration:1 Days |
Date Completed: |
Task Title:Device + Browser Testing |
Status: In Progress |
Start Date:06/02/2022 |
Due Date:06/03/2022 |
Duration:1 Days |
Date Completed: |
Task Title:Staging Site Client Review |
Status: In Progress |
Start Date:06/06/2022 |
Due Date:06/06/2022 |
Duration:1 Days |
Date Completed: |
Task Title:Final QA |
Status: In Progress |
Start Date:06/07/2022 |
Due Date:06/08/2022 |
Duration:1 Days |
Date Completed: |
Task Title:Launch 🚀 |
Status: In Progress |
Start Date:06/09/2022 |
Due Date:06/09/2022 |
Duration:1 Days |
Date Completed: |
Task Title:On Page SEO |
Status: Done |
Start Date:06/07/2022 |
Due Date:06/08/2022 |
Duration:1 Days |
Date Completed:06/21/2022 |
Task Title:Determine URLs and H1s |
Status: Done |
Start Date:06/07/2022 |
Due Date:06/08/2022 |
Duration:1 Days |
Date Completed:06/21/2022 |
Task Title:Implement custom metadescriptions |
Status: Done |
Start Date:06/07/2022 |
Due Date:06/08/2022 |
Duration:1 Days |
Date Completed:06/21/2022 |
Task Title:Post-Launch |
Status: On Deck |
Start Date:06/10/2022 |
Due Date:06/20/2022 |
Duration:10 Days |
Date Completed: |
Task Title:Domain Redirect www to non-www, Secure URL |
Status: Done |
Start Date:06/10/2022 |
Due Date:06/17/2022 |
Duration:7 Days |
Date Completed:06/21/2022 |
Task Title:Verify Site Form Submission Emails are Received by Client |
Status: On Deck |
Start Date:06/10/2022 |
Due Date:06/17/2022 |
Duration:7 Days |
Date Completed: |
Task Title:Client Training Videos and Login Access |
Status: On Deck |
Start Date:06/10/2022 |
Due Date:06/17/2022 |
Duration:7 Days |
Date Completed: |
Task Title:Post-Launch SEO |
Status: On Deck |
Start Date:06/10/2022 |
Due Date:06/17/2022 |
Duration:7 Days |
Date Completed: |
Task Title:Verify and Submit New Sitemap to Google Search Console |
Status: On Deck |
Start Date:06/10/2022 |
Due Date:06/17/2022 |
Duration:7 Days |
Date Completed: |
Task Title:Verify Data is Flowing into Google Analytics |
Status: On Deck |
Start Date:06/10/2022 |
Due Date:06/17/2022 |
Duration:7 Days |
Date Completed: |
Task Title:Verify Google Mobile Compliance & Screenshot |
Status: On Deck |
Start Date:06/10/2022 |
Due Date:06/17/2022 |
Duration:7 Days |
Date Completed: |