Task Title:Research |
Status: Done |
Start Date:11/29/2021 |
Due Date:03/02/2022 |
Duration:93 Days |
Date Completed:04/10/2022 |
Task Title:RMR Project Kickoff Questionnaire |
Status: Done |
Start Date:11/29/2021 |
Due Date:12/17/2021 |
Duration:18 Days |
Date Completed:12/21/2021 |
Task Title:RMR Project Kickoff Meeting |
Status: Done |
Start Date:12/21/2021 |
Due Date:12/21/2021 |
Duration:1 Days |
Date Completed:12/21/2021 |
Task Title:Collect Technical Files & Assets |
Status: Done |
Start Date:12/22/2021 |
Due Date:03/02/2022 |
Duration:70 Days |
Date Completed:04/05/2022 |
Task Title:Planning |
Status: Done |
Start Date:01/05/2022 |
Due Date:03/04/2022 |
Duration:58 Days |
Date Completed:04/10/2022 |
Task Title:Sitemap (v2) |
Status: Done |
Start Date:01/05/2022 |
Due Date:01/26/2022 |
Duration:21 Days |
Date Completed:01/26/2022 |
Task Title:Version 1 |
Status: Done |
Start Date:01/05/2022 |
Due Date:01/20/2022 |
Duration:15 Days |
Date Completed:01/20/2022 |
Task Title:Version 2 |
Status: Done |
Start Date:01/21/2022 |
Due Date:01/26/2022 |
Duration:5 Days |
Date Completed:01/26/2022 |
Task Title:Final Content Collection ✍️ |
Status: Done |
Start Date:01/13/2022 |
Due Date:03/04/2022 |
Duration:50 Days |
Date Completed:04/05/2022 |
Task Title:Home Page – Content Optimization |
Status: Done |
Start Date:02/10/2022 |
Due Date:02/25/2022 |
Duration:15 Days |
Date Completed:02/25/2022 |
Task Title:Content Optimization |
Status: Done |
Start Date:02/10/2022 |
Due Date:02/14/2022 |
Duration:4 Days |
Date Completed:02/25/2022 |
Task Title:RMR Review/Approval |
Status: Done |
Start Date:02/15/2022 |
Due Date:02/25/2022 |
Duration:10 Days |
Date Completed:02/25/2022 |
Task Title:Web Design |
Status: Done |
Start Date:02/28/2022 |
Due Date:05/06/2022 |
Duration:67 Days |
Date Completed:05/25/2022 |
Task Title:Home Page |
Status: Done |
Start Date:04/12/2022 |
Due Date:05/03/2022 |
Duration:21 Days |
Date Completed:04/20/2022 |
Task Title:Version 1 |
Status: Done |
Start Date:02/28/2022 |
Due Date:03/11/2022 |
Duration:11 Days |
Date Completed:03/14/2022 |
Task Title:Version 2 |
Status: Done |
Start Date:04/12/2022 |
Due Date:04/18/2022 |
Duration:6 Days |
Date Completed:04/20/2022 |
Task Title:Blog/Resources Detail |
Status: Done |
Start Date:04/18/2022 |
Due Date:05/18/2022 |
Duration:30 Days |
Date Completed:05/25/2022 |
Task Title:Version 1 |
Status: On Deck |
Start Date:04/18/2022 |
Due Date:05/06/2022 |
Duration:18 Days |
Date Completed: |
Task Title:Blog/Resources Landing Page |
Status: Done |
Start Date:04/18/2022 |
Due Date:05/19/2022 |
Duration:31 Days |
Date Completed:05/25/2022 |
Task Title:Version 1 |
Status: On Deck |
Start Date:04/18/2022 |
Due Date:05/06/2022 |
Duration:18 Days |
Date Completed: |
Task Title:Banners / Gallery / Detail Page |
Status: Done |
Start Date:04/18/2022 |
Due Date:05/06/2022 |
Duration:18 Days |
Date Completed:05/25/2022 |
Task Title:Version 1 |
Status: Done |
Start Date:04/18/2022 |
Due Date:05/06/2022 |
Duration:18 Days |
Date Completed:04/22/2022 |
Task Title:Web Dev |
Status: On Deck |
Start Date:05/16/2022 |
Due Date:07/05/2022 |
Duration:50 Days |
Date Completed: |
Task Title:Google Analytics Access from RMR to Chariot |
Status: Done |
Start Date:05/16/2022 |
Due Date:05/16/2022 |
Duration:1 Days |
Date Completed:05/20/2022 |
Task Title:Foundational Development / Coding |
Status: Done |
Start Date:05/16/2022 |
Due Date:05/27/2022 |
Duration:11 Days |
Date Completed:06/07/2022 |
Task Title:Page Templates + Generic Styles |
Status: Done |
Start Date:05/30/2022 |
Due Date:06/03/2022 |
Duration:4 Days |
Date Completed:06/07/2022 |
Task Title:Content Implementation |
Status: On Deck |
Start Date:06/06/2022 |
Due Date:06/13/2022 |
Duration:7 Days |
Date Completed: |
Task Title:Device + Browser Testing |
Status: On Deck |
Start Date:06/10/2022 |
Due Date:06/17/2022 |
Duration:7 Days |
Date Completed: |
Task Title:Developer QA |
Status: On Deck |
Start Date:06/10/2022 |
Due Date:06/14/2022 |
Duration:4 Days |
Date Completed: |
Task Title:Staging Site Review with RMR |
Status: On Deck |
Start Date:06/20/2022 |
Due Date:06/22/2022 |
Duration:2 Days |
Date Completed: |
Task Title:Final QA |
Status: On Deck |
Start Date:06/23/2022 |
Due Date:06/24/2022 |
Duration:1 Days |
Date Completed: |
Task Title:Launch 🚀 |
Status: On Deck |
Start Date:06/27/2022 |
Due Date:06/27/2022 |
Duration:1 Days |
Date Completed: |
Task Title:Post-Launch |
Status: On Deck |
Start Date:06/28/2022 |
Due Date:07/05/2022 |
Duration:7 Days |
Date Completed: |
Task Title:Verify Site Form Submission Emails are Received by RMR |
Status: On Deck |
Start Date:06/28/2022 |
Due Date:07/04/2022 |
Duration:6 Days |
Date Completed: |
Task Title:Exclude Team's IP address from RMR's Analytics |
Status: On Deck |
Start Date:06/28/2022 |
Due Date:07/04/2022 |
Duration:6 Days |
Date Completed: |
Task Title:Verify Google Mobile Compliance & Screenshot |
Status: On Deck |
Start Date:06/28/2022 |
Due Date:07/04/2022 |
Duration:6 Days |
Date Completed: |
Task Title:Verify and Submit New Sitemap to Google Search Console |
Status: On Deck |
Start Date:06/28/2022 |
Due Date:07/04/2022 |
Duration:6 Days |
Date Completed: |
Task Title:Verify Data is Flowing into Google Analytics |
Status: On Deck |
Start Date:06/28/2022 |
Due Date:07/04/2022 |
Duration:6 Days |
Date Completed: |
Task Title:RMR Training Videos and Login Access |
Status: On Deck |
Start Date:06/28/2022 |
Due Date:07/04/2022 |
Duration:6 Days |
Date Completed: |
Task Title:Domain Redirect www to non-www, Secure URL |
Status: On Deck |
Start Date:06/28/2022 |
Due Date:07/04/2022 |
Duration:6 Days |
Date Completed: |
Task Title:RMR Training Call |
Status: On Deck |
Start Date:07/05/2022 |
Due Date:07/05/2022 |
Duration:1 Days |
Date Completed: |