Open Projects

Overview Analytics • All Projects

  • 0% Completed
  • 0% In Progress
  • 0% Upcoming

Progress Overview • All Projects

Work
0%
Timeline
0%

0 Total Tasks Due This Week

PROJECT MPS - Web Design & Dev

Project Progress

  • 0% Completed
  • 0% In Progress
  • 0% On Deck

Project Status Overview

  • 0% Done
  • 0% In Progress
  • 0% On Deck
  • 0% Awaiting Client
  • 0% Rush
  • 0% Internal QA

Project Progress

Work
0%
Timeline
0%

0 Tasks Due This Week

Task Detail

Task Title Status Start Date Due Date Duration Date Completed
Task Title:DISCOVERY Status: Done Start Date:09/14/2022 Due Date:09/22/2022 Duration:8 Days Date Completed:09/22/2022
Task Title:MPS - Project Kickoff Questionnaire (Non-Profits) Status: Done Start Date: Due Date: Duration: Date Completed:09/22/2022
Task Title:Client Questionnaire Status: Done Start Date:09/14/2022 Due Date:09/19/2022 Duration:5 Days Date Completed:09/15/2022
Task Title:Client Kickoff Meeting Status: Done Start Date:09/20/2022 Due Date:09/20/2022 Duration:1 Days Date Completed:09/20/2022
Task Title:Collect Technical Files & Access Status: Done Start Date:09/21/2022 Due Date:09/23/2022 Duration:2 Days Date Completed:09/22/2022
Task Title:RESEARCH Status: Done Start Date:09/23/2022 Due Date:09/29/2022 Duration:6 Days Date Completed:09/28/2022
Task Title:SEO Research + KW Report Status: Done Start Date:09/23/2022 Due Date:09/28/2022 Duration:5 Days Date Completed:09/28/2022
Task Title:SITE PLANNING Status: Done Start Date:09/30/2022 Due Date:11/30/2022 Duration:61 Days Date Completed:01/31/2023
Task Title:Sitemap Status: Done Start Date:09/30/2022 Due Date:10/18/2022 Duration:18 Days Date Completed:10/19/2022
Task Title:Determine URLs for Sitemap Status: Done Start Date:09/30/2022 Due Date:10/03/2022 Duration:3 Days Date Completed:10/06/2022
Task Title:Sitemap Layout Status: Done Start Date:10/04/2022 Due Date:10/17/2022 Duration:13 Days Date Completed:10/19/2022
Task Title:Final Content Collection ✍️ Status: Done Start Date:10/18/2022 Due Date:11/30/2022 Duration:43 Days Date Completed:01/31/2023
Task Title:DESIGN Status: Done Start Date:12/01/2022 Due Date:02/06/2023 Duration:67 Days Date Completed:02/22/2023
Task Title:Home Page Design Status: Done Start Date:12/01/2022 Due Date:12/14/2022 Duration:13 Days Date Completed:12/30/2022
Task Title:Home Page Design + Layout Status: Done Start Date:12/01/2022 Due Date:12/07/2022 Duration:6 Days Date Completed:12/06/2022
Task Title:Internal Review / QA Status: Done Start Date:12/08/2022 Due Date:12/08/2022 Duration:1 Days Date Completed:12/06/2022
Task Title:Homepage / Direction Review with Client Status: Done Start Date:12/09/2022 Due Date:12/12/2022 Duration:3 Days Date Completed:12/12/2022
Task Title:v2 Homepage Design Status: Done Start Date:12/12/2022 Due Date:12/14/2022 Duration:2 Days Date Completed:12/22/2022
Task Title:Mobile Homepage + Mobile Nav Status: Done Start Date:12/13/2022 Due Date:12/14/2022 Duration:1 Days Date Completed:12/30/2022
Task Title:Disease Detail Page Design V3 Status: Done Start Date:12/15/2022 Due Date:02/06/2023 Duration:53 Days Date Completed:02/22/2023
Task Title:Membership / Sign Up Page Design V3 Status: Done Start Date:12/15/2022 Due Date:02/06/2023 Duration:53 Days Date Completed:02/22/2023
Task Title:Treatment Detail Page Design V3 Status: Done Start Date:12/15/2022 Due Date:02/06/2023 Duration:53 Days Date Completed:02/22/2023
Task Title:Give Page Design V3 Status: Done Start Date:12/15/2022 Due Date:02/06/2023 Duration:53 Days Date Completed:02/22/2023
Task Title:Donate Page Design V3 Status: Done Start Date:12/15/2022 Due Date:02/06/2023 Duration:53 Days Date Completed:02/22/2023
Task Title:Learn Page Design V3 Status: Done Start Date:12/15/2022 Due Date:02/06/2023 Duration:53 Days Date Completed:02/22/2023
Task Title:Fundraiser Event Registration Page (Form) V3 Status: Done Start Date:12/15/2022 Due Date:02/06/2023 Duration:53 Days Date Completed:02/22/2023
Task Title:Resources Landing Page Design V3 Status: Done Start Date:12/15/2022 Due Date:02/06/2023 Duration:53 Days Date Completed:02/22/2023
Task Title:Resources Detail Page Design V3 Status: Done Start Date:12/15/2022 Due Date:02/06/2023 Duration:53 Days Date Completed:02/22/2023
Task Title:Fundraiser Events Landing/Listing Page Design V3 Status: Done Start Date:12/15/2022 Due Date:02/06/2023 Duration:53 Days Date Completed:02/22/2023
Task Title:Advocacy Page Design V3 Status: Done Start Date:12/15/2022 Due Date:02/06/2023 Duration:53 Days Date Completed:02/22/2023
Task Title:Fundraiser Event Detail page V3 Status: Done Start Date:12/15/2022 Due Date:02/06/2023 Duration:53 Days Date Completed:02/22/2023
Task Title:DEVELOPMENT Status: In Progress Start Date:02/07/2023 Due Date:05/23/2023 Duration:105 Days Date Completed:
Task Title:Foundational Development / Coding Status: Done Start Date:02/07/2023 Due Date:02/17/2023 Duration:10 Days Date Completed:02/23/2023
Task Title:Flexible Content Blocks + Global CSS Status: Done Start Date:02/28/2023 Due Date:03/31/2023 Duration:31 Days Date Completed:03/28/2023
Task Title:Resources System complete with Category Filters and Tags in place Status: Internal QA Start Date:03/16/2023 Due Date:05/22/2023 Duration:67 Days Date Completed:
Task Title:Content Implementation Status: Done Start Date:04/03/2023 Due Date:05/16/2023 Duration:43 Days Date Completed:05/22/2023
Task Title:Assets + Content Migration Status: Internal QA Start Date:04/10/2023 Due Date:05/22/2023 Duration:42 Days Date Completed:
Task Title:Forms + Integration Status: Done Start Date:04/10/2023 Due Date:05/10/2023 Duration:30 Days Date Completed:05/22/2023
Task Title:Additional Fundraiser + Events System Status: In Progress Start Date:04/17/2023 Due Date:05/23/2023 Duration:36 Days Date Completed:
Task Title:Developer + Internal QA Status: In Progress Start Date:04/17/2023 Due Date:05/23/2023 Duration:36 Days Date Completed:
Task Title:Custom Remembrance Page Function with Draft / Approval Process Status: Done Start Date:04/17/2023 Due Date:05/22/2023 Duration:35 Days Date Completed:05/22/2023
Task Title:Content Implementation Status: Done Start Date:04/03/2023 Due Date:05/16/2023 Duration:43 Days Date Completed:05/22/2023
Task Title:Staging Site Client Review Status: Done Start Date:05/09/2023 Due Date:05/16/2023 Duration:7 Days Date Completed:05/22/2023
Task Title:Final Client Approval Status: Awaiting Approval Start Date:05/15/2023 Due Date:05/23/2023 Duration:8 Days Date Completed:
Task Title:Pre-Launch On-Page SEO Status: Done Start Date:05/16/2023 Due Date:05/19/2023 Duration:3 Days Date Completed:05/22/2023
Task Title:Client Admin Training Status: Awaiting Approval Start Date:05/16/2023 Due Date:05/25/2023 Duration:9 Days Date Completed:
Task Title:Membership & Registration with Payment Connection Status: Internal QA Start Date:05/17/2023 Due Date:05/22/2023 Duration:5 Days Date Completed:
Task Title:Simple Design for Membership Directory Status: Done Start Date:05/09/2023 Due Date:05/12/2023 Duration:3 Days Date Completed:05/31/2023
Task Title:Launch 🚀 Status: On Deck Start Date:05/19/2023 Due Date:05/22/2023 Duration:3 Days Date Completed:
Task Title:Post-Launch Verifications Status: On Deck Start Date:05/23/2023 Due Date:05/26/2023 Duration:3 Days Date Completed: