Task Title:Project Kickoff Call |
Status: Done |
Start Date:02/22/2022 |
Due Date:02/22/2022 |
Duration:1 Days |
Date Completed:02/23/2022 |
Task Title:Google Ads Set-Up |
Status: Done |
Start Date:02/28/2022 |
Due Date:03/14/2022 |
Duration:14 Days |
Date Completed:03/14/2022 |
Task Title:Implement Tracking Code into Website (if needed) |
Status: Done |
Start Date: |
Due Date: |
Duration: |
Date Completed:05/18/2022 |
Task Title:Click Ads + Campaigns Set-up |
Status: Done |
Start Date:02/28/2022 |
Due Date:03/14/2022 |
Duration:14 Days |
Date Completed:03/21/2022 |
Task Title:Display Ads |
Status: Done |
Start Date:02/28/2022 |
Due Date:03/14/2022 |
Duration:14 Days |
Date Completed:03/21/2022 |
Task Title:Display Ad Designs |
Status: Done |
Start Date:02/28/2022 |
Due Date:03/07/2022 |
Duration:7 Days |
Date Completed:03/04/2022 |
Task Title:Display Ad Set-Up in Google Ads |
Status: Done |
Start Date:03/24/2022 |
Due Date:03/24/2022 |
Duration:1 Days |
Date Completed:03/21/2022 |