Task Title:DISCOVERY |
Status: Done |
Start Date:07/08/2024 |
Due Date:07/18/2024 |
Duration:10 Days |
Date Completed:07/23/2024 |
Task Title:Project Setup |
Status: Done |
Start Date:07/08/2024 |
Due Date:07/12/2024 |
Duration:4 Days |
Date Completed:07/23/2024 |
Task Title:LWL Collect Branding Files & Access 🟢 |
Status: Done |
Start Date:07/15/2024 |
Due Date:07/18/2024 |
Duration:3 Days |
Date Completed:07/23/2024 |
Task Title:Kickoff + Discovery Meeting ☎️ |
Status: Done |
Start Date:07/16/2024 |
Due Date:07/16/2024 |
Duration:1 Days |
Date Completed:07/16/2024 |
Task Title:LWL Google Ads |
Status: Done |
Start Date:07/17/2024 |
Due Date:07/19/2024 |
Duration:2 Days |
Date Completed:07/23/2024 |
Task Title:LWL Google Ad Setup |
Status: Done |
Start Date:07/17/2024 |
Due Date:07/19/2024 |
Duration:2 Days |
Date Completed:07/23/2024 |
Task Title:RESEARCH |
Status: Done |
Start Date:07/19/2024 |
Due Date:07/30/2024 |
Duration:11 Days |
Date Completed:07/30/2024 |
Task Title:SEO Research + KW Report |
Status: Done |
Start Date:07/19/2024 |
Due Date:07/30/2024 |
Duration:11 Days |
Date Completed:07/30/2024 |
Task Title:LWL KWR: Prepare v1 |
Status: Done |
Start Date:07/22/2024 |
Due Date:07/22/2024 |
Duration:1 Days |
Date Completed:07/22/2024 |
Task Title:LWL KWR Client Review |
Status: Done |
Start Date:07/24/2024 |
Due Date:07/24/2024 |
Duration:1 Days |
Date Completed:07/24/2024 |
Task Title:LWL KWR v2 |
Status: Done |
Start Date:07/24/2024 |
Due Date:07/24/2024 |
Duration:1 Days |
Date Completed:07/25/2024 |
Task Title:LWL Client Approval |
Status: Done |
Start Date:07/29/2024 |
Due Date:07/29/2024 |
Duration:1 Days |
Date Completed:07/30/2024 |
Task Title:SITE PLANNING |
Status: Done |
Start Date:07/29/2024 |
Due Date:09/26/2024 |
Duration:59 Days |
Date Completed:09/25/2024 |
Task Title:Sitemap Strategy + Outline |
Status: Done |
Start Date:07/29/2024 |
Due Date:07/31/2024 |
Duration:2 Days |
Date Completed:08/01/2024 |
Task Title:LWL Sitemap Design |
Status: Done |
Start Date:08/01/2024 |
Due Date:08/08/2024 |
Duration:7 Days |
Date Completed:08/07/2024 |
Task Title:LWL Sitemap Client Review ☎️ |
Status: Done |
Start Date:08/01/2024 |
Due Date:08/05/2024 |
Duration:4 Days |
Date Completed:08/05/2024 |
Task Title:LWL Sitemap Design V1 |
Status: Done |
Start Date:08/01/2024 |
Due Date:08/01/2024 |
Duration:1 Days |
Date Completed:08/02/2024 |
Task Title:LWL Sitemap V2 (Optional Revisions) |
Status: Done |
Start Date:08/05/2024 |
Due Date:08/05/2024 |
Duration:1 Days |
Date Completed:08/06/2024 |
Task Title:LWL Sitemap V3 (Final Revisions) |
Status: Done |
Start Date:08/06/2024 |
Due Date:08/06/2024 |
Duration:1 Days |
Date Completed:08/06/2024 |
Task Title:Content Collection 🟢 |
Status: Done |
Start Date:08/09/2024 |
Due Date:09/26/2024 |
Duration:48 Days |
Date Completed:09/25/2024 |
Task Title:LWL Copywriting Draft v1 |
Status: Done |
Start Date:08/09/2024 |
Due Date:09/06/2024 |
Duration:28 Days |
Date Completed:09/06/2024 |
Task Title:LWL Client Draft 1 Review |
Status: Done |
Start Date:09/09/2024 |
Due Date:09/16/2024 |
Duration:7 Days |
Date Completed:09/17/2024 |
Task Title:LWL Copywriting Draft v2 (optional) |
Status: Done |
Start Date:09/17/2024 |
Due Date:09/25/2024 |
Duration:8 Days |
Date Completed:09/25/2024 |
Task Title:LWL Copywriting v3 (final) |
Status: Cancelled |
Start Date:09/26/2024 |
Due Date:09/26/2024 |
Duration:1 Days |
Date Completed: |
Task Title:Chatbot- Research |
Status: Done |
Start Date:07/29/2024 |
Due Date:07/30/2024 |
Duration:1 Days |
Date Completed:08/05/2024 |
Task Title:LWL Google Ads Biweekly Updates |
Status: On Deck |
Start Date:08/01/2024 |
Due Date:11/01/2024 |
Duration:92 Days |
Date Completed: |
Task Title:LWL Bi-Weekly Update #1 |
Status: Done |
Start Date:08/05/2024 |
Due Date:08/05/2024 |
Duration:1 Days |
Date Completed:08/05/2024 |
Task Title:LWL Bi-Weekly Update #2 |
Status: Done |
Start Date:08/16/2024 |
Due Date:08/16/2024 |
Duration:1 Days |
Date Completed:08/15/2024 |
Task Title:LWL Bi-Weekly Update #3 |
Status: Done |
Start Date:09/17/2024 |
Due Date:09/17/2024 |
Duration:1 Days |
Date Completed:09/17/2024 |
Task Title:LWL Bi-Weekly Update #4 |
Status: On Deck |
Start Date:10/16/2024 |
Due Date:10/16/2024 |
Duration:1 Days |
Date Completed: |
Task Title:Quote for scope expansion of 9-10 pages |
Status: Done |
Start Date:08/01/2024 |
Due Date:08/01/2024 |
Duration:1 Days |
Date Completed:08/29/2024 |
Task Title:Google Ads Update |
Status: Done |
Start Date:08/02/2024 |
Due Date:08/02/2024 |
Duration:1 Days |
Date Completed:08/04/2024 |
Task Title:DESIGN + DEVELOPMENT |
Status: In Progress |
Start Date:08/21/2024 |
Due Date:11/15/2024 |
Duration:86 Days |
Date Completed: |
Task Title:Homepage Design + Nav |
Status: Awaiting Client |
Start Date:08/21/2024 |
Due Date:10/14/2024 |
Duration:54 Days |
Date Completed: |
Task Title:LWL Homepage + Nav v1 |
Status: Done |
Start Date:08/21/2024 |
Due Date:09/13/2024 |
Duration:23 Days |
Date Completed:09/17/2024 |
Task Title:LWL Homepage Design Client Review ☎️ |
Status: Done |
Start Date:09/18/2024 |
Due Date:09/26/2024 |
Duration:8 Days |
Date Completed:09/26/2024 |
Task Title:LWL Homepage + Nav v2 (optional revisions) |
Status: Awaiting Client |
Start Date:10/04/2024 |
Due Date:10/11/2024 |
Duration:7 Days |
Date Completed: |
Task Title:LWL Homepage + Nav v3 (optional/ final) |
Status: Awaiting Client |
Start Date:10/14/2024 |
Due Date:10/14/2024 |
Duration:1 Days |
Date Completed: |
Task Title:LWL UI Style Guide + Prep |
Status: Done |
Start Date:09/24/2024 |
Due Date:09/24/2024 |
Duration:1 Days |
Date Completed:09/24/2024 |
Task Title:LWL Media Sourcing |
Status: In Progress |
Start Date:10/11/2024 |
Due Date:10/11/2024 |
Duration:1 Days |
Date Completed: |
Task Title:All Pages Build + Blog |
Status: On Deck |
Start Date:10/14/2024 |
Due Date:11/07/2024 |
Duration:24 Days |
Date Completed: |
Task Title:LWL Pages Buildout V1 |
Status: On Deck |
Start Date:10/15/2024 |
Due Date:10/23/2024 |
Duration:8 Days |
Date Completed: |
Task Title:LWL Internal QA |
Status: On Deck |
Start Date:10/24/2024 |
Due Date:10/28/2024 |
Duration:4 Days |
Date Completed: |
Task Title:LWL Staging Client Review ☎️ |
Status: On Deck |
Start Date:10/29/2024 |
Due Date:10/31/2024 |
Duration:2 Days |
Date Completed: |
Task Title:LWL Staging Edits V2 (Optional Revisions) |
Status: On Deck |
Start Date:11/01/2024 |
Due Date:11/05/2024 |
Duration:4 Days |
Date Completed: |
Task Title:LWL Staging Edits V3 (Final Revisions) |
Status: On Deck |
Start Date:11/06/2024 |
Due Date:11/07/2024 |
Duration:1 Days |
Date Completed: |
Task Title:On-Page SEO |
Status: On Deck |
Start Date:11/08/2024 |
Due Date:11/12/2024 |
Duration:4 Days |
Date Completed: |
Task Title:Client Training & Access |
Status: On Deck |
Start Date:11/13/2024 |
Due Date:11/13/2024 |
Duration:1 Days |
Date Completed: |
Task Title:Launch 🚀 |
Status: On Deck |
Start Date:11/14/2024 |
Due Date:11/14/2024 |
Duration:1 Days |
Date Completed: |
Task Title:Post-Launch Followup copy |
Status: On Deck |
Start Date:11/15/2024 |
Due Date:11/15/2024 |
Duration:1 Days |
Date Completed: |
Task Title:LWL Blogs |
Status: In Progress |
Start Date:09/03/2024 |
Due Date:10/21/2024 |
Duration:48 Days |
Date Completed: |
Task Title:Blog Topic Research |
Status: Done |
Start Date:09/03/2024 |
Due Date:09/09/2024 |
Duration:6 Days |
Date Completed:09/24/2024 |
Task Title:Pre-Launch Blog #1 |
Status: Done |
Start Date:09/16/2024 |
Due Date:09/26/2024 |
Duration:10 Days |
Date Completed:09/24/2024 |
Task Title:Pre-Launch Blog #1 Copywriting |
Status: Done |
Start Date:09/16/2024 |
Due Date:09/19/2024 |
Duration:3 Days |
Date Completed:09/13/2024 |
Task Title:Send Blog for Approval |
Status: Done |
Start Date:09/24/2024 |
Due Date:09/25/2024 |
Duration:1 Days |
Date Completed:09/24/2024 |
Task Title:Pre- Launch Blog #2 |
Status: Awaiting Client |
Start Date:09/27/2024 |
Due Date:10/07/2024 |
Duration:10 Days |
Date Completed: |
Task Title:Pre-Launch Blog #2 Copywriting |
Status: Done |
Start Date:09/27/2024 |
Due Date:10/03/2024 |
Duration:6 Days |
Date Completed:09/24/2024 |
Task Title:Send Blog for Approval |
Status: Awaiting Client |
Start Date:10/04/2024 |
Due Date:10/07/2024 |
Duration:3 Days |
Date Completed: |
Task Title:Pre-Launch Blog #3 |
Status: On Deck |
Start Date:10/08/2024 |
Due Date:10/14/2024 |
Duration:6 Days |
Date Completed: |
Task Title:Pre-Launch Blog #3 Copywriting |
Status: Done |
Start Date:10/08/2024 |
Due Date:10/10/2024 |
Duration:2 Days |
Date Completed:10/09/2024 |
Task Title:Send Blog for Approval |
Status: On Deck |
Start Date:10/11/2024 |
Due Date:10/14/2024 |
Duration:3 Days |
Date Completed: |
Task Title:Pre-Launch Blog #4 |
Status: On Deck |
Start Date:10/15/2024 |
Due Date:10/21/2024 |
Duration:6 Days |
Date Completed: |
Task Title:Pre-Launch Blog #4 Copywriting |
Status: On Deck |
Start Date:10/15/2024 |
Due Date:10/17/2024 |
Duration:2 Days |
Date Completed: |
Task Title:Send Blog for Approval |
Status: On Deck |
Start Date:10/18/2024 |
Due Date:10/21/2024 |
Duration:3 Days |
Date Completed: |
Task Title:QUOTE: Photography Services |
Status: Awaiting Client |
Start Date:09/24/2024 |
Due Date:09/26/2024 |
Duration:2 Days |
Date Completed: |
Task Title:Blog: LWL November 1/2 |
Status: On Deck |
Start Date:11/01/2024 |
Due Date:11/13/2024 |
Duration:12 Days |
Date Completed: |
Task Title:Research and Write LWL November 1/2 Blog |
Status: On Deck |
Start Date:11/01/2024 |
Due Date:11/07/2024 |
Duration:6 Days |
Date Completed: |
Task Title:Send Blog for Approval |
Status: On Deck |
Start Date:11/08/2024 |
Due Date:11/12/2024 |
Duration:4 Days |
Date Completed: |
Task Title:Publish Client Approved Blog |
Status: On Deck |
Start Date:11/13/2024 |
Due Date:11/13/2024 |
Duration:1 Days |
Date Completed: |
Task Title:Blog: LWL November 2/2 |
Status: On Deck |
Start Date:11/15/2024 |
Due Date:11/27/2024 |
Duration:12 Days |
Date Completed: |
Task Title:Research and Write LWL November 2/2 Blog |
Status: On Deck |
Start Date:11/15/2024 |
Due Date:11/21/2024 |
Duration:6 Days |
Date Completed: |
Task Title:Send Blog for Approval |
Status: On Deck |
Start Date:11/22/2024 |
Due Date:11/26/2024 |
Duration:4 Days |
Date Completed: |
Task Title:Publish Client Approved Blog |
Status: On Deck |
Start Date:11/27/2024 |
Due Date:11/27/2024 |
Duration:1 Days |
Date Completed: |
Task Title:Create Monthly Blog Cards for 2025 |
Status: On Deck |
Start Date:11/21/2024 |
Due Date:11/21/2024 |
Duration:1 Days |
Date Completed: |