Overview Analytics • All Projects

  • 0% Completed
  • 0% In Progress
  • 0% Upcoming

Progress Overview • All Projects

Work
0%
Timeline
0%

0 Total Tasks Due This Week

PROJECT Dueling Dinosaurs Website Redesign + Dev 2023

Project Progress

  • 0% Completed
  • 0% In Progress
  • 0% On Deck

Project Status Overview

  • 0% Done
  • 0% In Progress
  • 0% On Deck
  • 0% Awaiting Client
  • 0% Rush
  • 0% Internal QA

Project Progress

Work
0%
Timeline
0%

0 Tasks Due This Week

Task Detail

Task Title Status Start Date Due Date Duration Date Completed
Task Title:DISCOVERY Status: Done Start Date:03/15/2023 Due Date:05/01/2023 Duration:47 Days Date Completed:06/01/2023
Task Title:Kickoff + Discovery Meeting Status: Done Start Date:03/20/2023 Due Date:03/22/2023 Duration:2 Days Date Completed:03/17/2023
Task Title:Collect Technical Files & Access Status: Done Start Date:03/22/2023 Due Date:04/28/2023 Duration:37 Days Date Completed:06/01/2023
Task Title:SITE PLANNING Status: In Progress Start Date:03/15/2023 Due Date:06/30/2023 Duration:107 Days Date Completed:
Task Title:Sitemap Status: Done Start Date:04/10/2023 Due Date:05/12/2023 Duration:32 Days Date Completed:05/18/2023
Task Title:Final Content Collection ✍️ Status: In Progress Start Date:05/09/2023 Due Date:06/30/2023 Duration:52 Days Date Completed:
Task Title:DESIGN Status: On Deck Start Date:07/03/2023 Due Date:08/02/2023 Duration:30 Days Date Completed:
Task Title:Home Page Design Status: On Deck Start Date:07/03/2023 Due Date:07/18/2023 Duration:15 Days Date Completed:
Task Title:Mobile Homepage & Mobile Nav Status: On Deck Start Date:07/03/2023 Due Date:07/06/2023 Duration:3 Days Date Completed:
Task Title:Home Page for Internal Review Status: On Deck Start Date:07/10/2023 Due Date:07/13/2023 Duration:3 Days Date Completed:
Task Title:Homepage Review with Client (Call) Status: On Deck Start Date:07/14/2023 Due Date:07/18/2023 Duration:4 Days Date Completed:
Task Title:Subpage Design Status: On Deck Start Date:07/19/2023 Due Date:08/02/2023 Duration:14 Days Date Completed:
Task Title:Timeline / Dinosaurs / The Team Page Status: On Deck Start Date:07/19/2023 Due Date:07/28/2023 Duration:9 Days Date Completed:
Task Title:Blog/News Landing Page Status: On Deck Start Date:07/19/2023 Due Date:07/28/2023 Duration:9 Days Date Completed:
Task Title:Article Detail Page Status: On Deck Start Date:07/19/2023 Due Date:07/28/2023 Duration:9 Days Date Completed:
Task Title:UI Style Guide + Prep for Development Status: On Deck Start Date:07/19/2023 Due Date:07/25/2023 Duration:6 Days Date Completed:
Task Title:DEVELOPMENT Status: On Deck Start Date:08/07/2023 Due Date:09/25/2023 Duration:49 Days Date Completed:
Task Title:Technical Dev Brief Status: On Deck Start Date:08/07/2023 Due Date:08/11/2023 Duration:4 Days Date Completed:
Task Title:Foundational Development / Coding Status: On Deck Start Date:08/14/2023 Due Date:08/22/2023 Duration:8 Days Date Completed:
Task Title:Resources System Status: On Deck Start Date:08/23/2023 Due Date:08/28/2023 Duration:5 Days Date Completed:
Task Title:Content Migration Status: On Deck Start Date:08/29/2023 Due Date:09/05/2023 Duration:7 Days Date Completed:
Task Title:Flexible Content System Status: On Deck Start Date:08/29/2023 Due Date:08/31/2023 Duration:2 Days Date Completed:
Task Title:UI Animations and Integrations Status: On Deck Start Date:09/01/2023 Due Date:09/05/2023 Duration:4 Days Date Completed:
Task Title:Content Implementation Status: On Deck Start Date:09/01/2023 Due Date:09/05/2023 Duration:4 Days Date Completed:
Task Title:Developer QA Status: On Deck Start Date:09/06/2023 Due Date:09/07/2023 Duration:1 Days Date Completed:
Task Title:Pre-Launch On-Page SEO Status: On Deck Start Date:09/08/2023 Due Date:09/11/2023 Duration:3 Days Date Completed:
Task Title:Staging Site Client Review Status: On Deck Start Date:09/12/2023 Due Date:09/12/2023 Duration:1 Days Date Completed:
Task Title:Final QA + Updates Status: On Deck Start Date:09/13/2023 Due Date:09/15/2023 Duration:2 Days Date Completed:
Task Title:Launch 🚀 Status: On Deck Start Date:09/18/2023 Due Date:09/20/2023 Duration:2 Days Date Completed:
Task Title:Post-Launch Verifications Status: On Deck Start Date:09/21/2023 Due Date:09/21/2023 Duration:1 Days Date Completed:
Task Title:Client Admin Training Status: On Deck Start Date:09/22/2023 Due Date:09/25/2023 Duration:3 Days Date Completed: