• Client Dashboard
  • |
  • DisposeRx

This dashboard was hand-crafted and custom built by Chariot... because we appreciate our clients!

  • Saturday, February 4, 2023

PRINT

Open Projects

Overview Analytics • All Projects

  • 0% Completed
  • 0% In Progress
  • 0% Upcoming

Progress Overview • All Projects

Work
0%
Timeline
0%

0 Total Tasks Due This Week

PROJECT DRX - Web Design

Project Progress

  • 0% Completed
  • 0% In Progress
  • 0% On Deck

Project Status Overview

  • 0% Done
  • 0% In Progress
  • 0% On Deck
  • 0% Awaiting Client
  • 0% Rush
  • 0% Internal QA

Project Progress

Work
0%
Timeline
0%

0 Tasks Due This Week

Task Detail

Task Title Status Start Date Due Date Duration Date Completed
Task Title:DISCOVERY Status: Done Start Date:05/23/2022 Due Date:05/31/2022 Duration:8 Days Date Completed:07/05/2022
Task Title:Dispose Rx: Project Kickoff Questionnaire Status: Done Start Date: Due Date: Duration: Date Completed:09/22/2022
Task Title:Client Questionnaire Status: Done Start Date:05/23/2022 Due Date:05/25/2022 Duration:2 Days Date Completed:06/06/2022
Task Title:Client Kickoff Meeting Status: Done Start Date:05/26/2022 Due Date:05/26/2022 Duration:1 Days Date Completed:05/26/2022
Task Title:Collect Technical Files & Access Status: Done Start Date:05/27/2022 Due Date:05/31/2022 Duration:4 Days Date Completed:07/05/2022
Task Title:SITE PLANNING Status: Done Start Date:08/12/2022 Due Date:11/18/2022 Duration:98 Days Date Completed:11/15/2022
Task Title:Sitemap Status: Done Start Date:08/12/2022 Due Date:08/23/2022 Duration:11 Days Date Completed:08/16/2022
Task Title:Sitemap Layout Status: Done Start Date:07/06/2022 Due Date:07/11/2022 Duration:5 Days Date Completed:08/16/2022
Task Title:Final Content Collection ✍️ Status: Done Start Date:10/10/2022 Due Date:11/18/2022 Duration:39 Days Date Completed:11/15/2022
Task Title:DESIGN Status: Done Start Date:11/21/2022 Due Date:01/06/2023 Duration:46 Days Date Completed:01/24/2023
Task Title:Home Page Design Status: Done Start Date:11/21/2022 Due Date:12/15/2022 Duration:24 Days Date Completed:01/12/2023
Task Title:Home Page Design + Layout Status: Done Start Date:11/21/2022 Due Date:11/25/2022 Duration:4 Days Date Completed:11/30/2022
Task Title:Internal Review / QA Status: Done Start Date:11/28/2022 Due Date:11/28/2022 Duration:1 Days Date Completed:11/30/2022
Task Title:Homepage / Direction Review with Client Status: Done Start Date:11/30/2022 Due Date:12/02/2022 Duration:2 Days Date Completed:12/08/2022
Task Title:v2 Homepage Design Status: Done Start Date:12/08/2022 Due Date:12/08/2022 Duration:1 Days Date Completed:12/15/2022
Task Title:Web Page 2 - Products Page Status: Done Start Date:12/16/2022 Due Date:12/20/2022 Duration:4 Days Date Completed:01/24/2023
Task Title:Design + Layout Status: Done Start Date:12/16/2022 Due Date:12/19/2022 Duration:3 Days Date Completed:01/12/2023
Task Title:Internal Review / QA Status: Done Start Date:12/20/2022 Due Date:12/20/2022 Duration:1 Days Date Completed:01/12/2023
Task Title:Web Page 3 - Packet Information Status: Done Start Date:12/21/2022 Due Date:12/23/2022 Duration:2 Days Date Completed:01/24/2023
Task Title:Design + Layout Status: Done Start Date:12/21/2022 Due Date:12/22/2022 Duration:1 Days Date Completed:01/12/2023
Task Title:Internal Review / QA Status: Done Start Date:12/23/2022 Due Date:12/23/2022 Duration:1 Days Date Completed:01/12/2023
Task Title:Web Page 5 - Health Systems Status: Done Start Date:12/26/2022 Due Date:12/28/2022 Duration:2 Days Date Completed:01/24/2023
Task Title:Design + Layout Status: Done Start Date:12/26/2022 Due Date:12/27/2022 Duration:1 Days Date Completed:01/12/2023
Task Title:Internal Review / QA Status: Done Start Date:12/28/2022 Due Date:12/28/2022 Duration:1 Days Date Completed:01/12/2023
Task Title:Web Page 4 - Healthcare Providers Status: Done Start Date:12/26/2022 Due Date:12/28/2022 Duration:2 Days Date Completed:01/24/2023
Task Title:Design + Layout Status: Done Start Date:12/26/2022 Due Date:12/27/2022 Duration:1 Days Date Completed:01/12/2023
Task Title:Internal Review / QA Status: Done Start Date:12/28/2022 Due Date:12/28/2022 Duration:1 Days Date Completed:01/12/2023
Task Title:UI Style Guide Status: Done Start Date:12/29/2022 Due Date:12/30/2022 Duration:1 Days Date Completed:01/24/2023
Task Title:Mobile Homepage + Mobile Nav Status: Done Start Date:01/23/2023 Due Date:01/25/2023 Duration:2 Days Date Completed:01/31/2023
Task Title:Design + Layout Status: Done Start Date:01/23/2023 Due Date:01/24/2023 Duration:1 Days Date Completed:01/31/2023
Task Title:Internal Review / QA Status: Done Start Date:01/25/2023 Due Date:01/25/2023 Duration:1 Days Date Completed:01/31/2023
Task Title:UI Style Kit + Handoff Status: Awaiting Approval Start Date:01/09/2023 Due Date:01/13/2023 Duration:4 Days Date Completed: