Open Projects

Overview Analytics • All Projects

  • 0% Completed
  • 0% In Progress
  • 0% Upcoming

Progress Overview • All Projects

Work
0%
Timeline
0%

0 Total Tasks Due This Week

PROJECT Anne Till Nutrition Group

Project Progress

  • 0% Completed
  • 0% In Progress
  • 0% On Deck

Project Status Overview

  • 0% Done
  • 0% In Progress
  • 0% On Deck
  • 0% Awaiting Client
  • 0% Rush
  • 0% Internal QA

Project Progress

Work
0%
Timeline
0%

0 Tasks Due This Week

Task Detail

Task Title Status Start Date Due Date Duration Date Completed
Task Title:DISCOVERY Status: Done Start Date:09/27/2023 Due Date:10/12/2023 Duration:15 Days Date Completed:10/26/2023
Task Title:Project Setup Status: Done Start Date:09/27/2023 Due Date:09/28/2023 Duration:1 Days Date Completed:10/03/2023
Task Title:Kickoff + Discovery Meeting ☎️ Status: Done Start Date:10/03/2023 Due Date:10/03/2023 Duration:1 Days Date Completed:10/03/2023
Task Title:Collect Branding Files & Access 🟢 Status: Done Start Date:10/04/2023 Due Date:10/12/2023 Duration:8 Days Date Completed:10/24/2023
Task Title:GA4 Review Status: Done Start Date:10/12/2023 Due Date:10/13/2023 Duration:1 Days Date Completed:10/12/2023
Task Title:SITE PLANNING Status: Done Start Date:10/13/2023 Due Date:11/20/2023 Duration:38 Days Date Completed:11/27/2023
Task Title:Sitemap Status: Done Start Date:10/13/2023 Due Date:11/20/2023 Duration:38 Days Date Completed:11/27/2023
Task Title:Content Collection 🟢 Status: Done Start Date:10/13/2023 Due Date:11/20/2023 Duration:38 Days Date Completed:11/20/2023
Task Title:DESIGN + DEVELOPMENT Status: In Progress Start Date:11/21/2023 Due Date:01/10/2024 Duration:50 Days Date Completed:
Task Title:UI Style Guide + Prep Status: Done Start Date:11/21/2023 Due Date:11/29/2023 Duration:8 Days Date Completed:12/01/2023
Task Title:Homepage Figma Design + Foundation Buildout Status: Awaiting Approval Start Date:11/30/2023 Due Date:12/11/2023 Duration:11 Days Date Completed:
Task Title:Homepage Design Client Review ☎️ Status: Done Start Date:12/05/2023 Due Date:12/05/2023 Duration:1 Days Date Completed:12/05/2023
Task Title:Sub Page Buildout Status: On Deck Start Date:12/12/2023 Due Date:12/19/2023 Duration:7 Days Date Completed:
Task Title:Content Implementation Status: On Deck Start Date:12/20/2023 Due Date:12/26/2023 Duration:6 Days Date Completed:
Task Title:Internal QA Status: On Deck Start Date:12/27/2023 Due Date:12/29/2023 Duration:2 Days Date Completed:
Task Title:Presentation + Client Review ☎️ Status: On Deck Start Date:01/02/2024 Due Date:01/03/2024 Duration:1 Days Date Completed:
Task Title:Client Training & Access Status: On Deck Start Date:01/04/2024 Due Date:01/05/2024 Duration:1 Days Date Completed:
Task Title:Launch 🚀 Status: On Deck Start Date:01/04/2024 Due Date:01/05/2024 Duration:1 Days Date Completed:
Task Title:Post-Launch Followup copy Status: On Deck Start Date:01/08/2024 Due Date:01/09/2024 Duration:1 Days Date Completed: