• Client Dashboard
  • |
  • Anne Till Nutrition Group

This dashboard was hand-crafted and custom built by Chariot... because we appreciate our clients!

  • Wednesday, June 19, 2024

PRINT

Open Projects

Overview Analytics • All Projects

  • 0% Completed
  • 0% In Progress
  • 0% Upcoming

Progress Overview • All Projects

Work
0%
Timeline
0%

0 Total Tasks Due This Week

PROJECT ATNG Website

Project Progress

  • 0% Completed
  • 0% In Progress
  • 0% On Deck

Project Status Overview

  • 0% Done
  • 0% In Progress
  • 0% On Deck
  • 0% Awaiting Client
  • 0% Internal QA

Project Progress

Work
0%
Timeline
0%

0 Tasks Due This Week

Task Detail

Task Title Status Start Date Due Date Duration Date Completed
Task Title:DISCOVERY Status: Done Start Date:09/27/2023 Due Date:10/12/2023 Duration:15 Days Date Completed:10/26/2023
Task Title:Project Setup Status: Done Start Date:09/27/2023 Due Date:09/28/2023 Duration:1 Days Date Completed:10/03/2023
Task Title:Kickoff + Discovery Meeting ☎️ Status: Done Start Date:10/03/2023 Due Date:10/03/2023 Duration:1 Days Date Completed:10/03/2023
Task Title:Collect Branding Files & Access 🟢 Status: Done Start Date:10/04/2023 Due Date:10/12/2023 Duration:8 Days Date Completed:10/24/2023
Task Title:GA4 Review Status: Done Start Date:10/12/2023 Due Date:10/13/2023 Duration:1 Days Date Completed:10/12/2023
Task Title:SITE PLANNING Status: Done Start Date:10/13/2023 Due Date:11/20/2023 Duration:38 Days Date Completed:11/27/2023
Task Title:Sitemap Status: Done Start Date:10/13/2023 Due Date:11/20/2023 Duration:38 Days Date Completed:11/27/2023
Task Title:Content Collection 🟢 Status: Done Start Date:10/13/2023 Due Date:11/20/2023 Duration:38 Days Date Completed:11/20/2023
Task Title:DESIGN + DEVELOPMENT Status: Awaiting Client Start Date:12/05/2023 Due Date:06/26/2024 Duration:204 Days Date Completed:
Task Title:Homepage Design Client Review ☎️ Status: Done Start Date:12/05/2023 Due Date:12/05/2023 Duration:1 Days Date Completed:12/05/2023
Task Title:UI Style Guide + Prep Status: Done Start Date:01/23/2024 Due Date:01/26/2024 Duration:3 Days Date Completed:01/26/2024
Task Title:dev brief Status: Done Start Date:01/26/2024 Due Date:01/30/2024 Duration:4 Days Date Completed:01/29/2024
Task Title:Homepage Figma Design + Foundation Buildout Status: Done Start Date:01/29/2024 Due Date:02/23/2024 Duration:25 Days Date Completed:02/28/2024
Task Title:Sub Page Buildout Status: Done Start Date:02/26/2024 Due Date:03/11/2024 Duration:14 Days Date Completed:03/11/2024
Task Title:Content Implementation Status: Done Start Date:03/12/2024 Due Date:03/14/2024 Duration:2 Days Date Completed:03/11/2024
Task Title:Internal QA Status: Done Start Date:03/15/2024 Due Date:03/19/2024 Duration:4 Days Date Completed:03/20/2024
Task Title:Presentation + Client Review ☎️ Status: Awaiting Client Start Date:03/21/2024 Due Date:06/10/2024 Duration:81 Days Date Completed:
Task Title:Staging edits V2 (optional) Status: Awaiting Client Start Date:06/11/2024 Due Date:06/14/2024 Duration:3 Days Date Completed:
Task Title:Staging Edits V3 (optional/final) Status: Awaiting Client Start Date:06/17/2024 Due Date:06/20/2024 Duration:3 Days Date Completed:
Task Title:Client Training & Access Status: Internal QA/Approval Start Date:06/21/2024 Due Date:06/24/2024 Duration:3 Days Date Completed:
Task Title:Launch 🚀 Status: Awaiting Client Start Date:06/25/2024 Due Date:06/25/2024 Duration:1 Days Date Completed:
Task Title:Post-Launch Follow up copy Status: Awaiting Client Start Date:06/26/2024 Due Date:06/26/2024 Duration:1 Days Date Completed: